Rare event risks make or break any capital project because we handle them poorly. By contrast, traditional project risks are handled well in the engineering and construction industry.
Project risks occur as a matter of course on every major facility and infrastructure project. Five years from engineering through construction is a good breakpoint for the difference between minor and major projects. Modeling of project risks is usually performed with probability distributions based on historical experience with aspects such as cost and schedule.
Rare event categories include Economic, Informational, Physical (key equipment), Human Resource, Reputational, Psychopathic Acts, and Natural Disasters. Another description can be extreme events. The thought process for including them is “externally driven.” Modeling of rare events is performed with a Bernoulli distribution (occurring over the project life cycle or not, on a one-time basis) or a Poisson distribution (occurring over the project life cycle or not, potentially more than once).
One example to consider when deciding whether an event is a rare event risk, or a traditional project risk is flooding. If your project is near or partially in a 100-year floodplain, the chance of being flooded in any one year is 0.01. However, the chance of being flooded over the life of a 30-year mortgage is 26% [Probability = 1-(1-p)^N]. For most projects of less than 10 years, they can be classified as a rare event (and probably not the most impactful in the Natural Disaster category). But if you are an owner or investor with a 30- to 50-year perspective, the risk is something you should consider as a project risk.
If the project duration matters, so does the project location. Mobile, Alabama, or New Orleans, Louisiana experience a minor hurricane (category 1 or 2) almost every year. Consider it a project risk on major projects. Major hurricanes (category 3, 4, or 5) that make landfall occur much less frequently. Consider a major hurricane as a rare event (and probably the most significant one in the Natural Disaster category) if you are in Mobile or New Orleans and doing a 5- to 7-year duration project.
Under the human resources category, a turnover of elected officials usually provides the greatest impact on major public projects. Turnover results in delays while new members questions previous decisions, re-scoping of the project, or killing the project. It is common to lose one or two elected officials so in practice this occurrence should be considered as a project risk. Having the turnover of a majority of elected commissioners is usually a rare event on most projects less than 10 years in duration.
Delays of long-lead equipment like we have seen during the global pandemic may come to mind as a rare event in the Physical (key equipment) category. But be careful – supply chain issues and resulting delays should be expected on any major project. The magnitude of the delay is probably the best tipping point to decide between a project risk or a rare event in this case.
Good practice is usually to list and analyze rare events separately from project risks. One reason for doing this is that mitigation planning can be done differently, and not solely as a financial contingency. For example, the potential rare event of Board Turnover was identified early on a Clean Energy project I did a decade ago for a pro-green City Council. By recognizing the rare event early, we were able to mitigate the potential risk by incorporating pro-business approaches into the project. The rare event did occur, but we were able to navigate seamlessly through the transition without additional cost or delay.
Remember that context matters most. And what was rare yesterday may not be rare tomorrow. In the end, you will have to decide on a case-specific basis things like the quality of the flood mapping prediction and mapping, whether a direct hit by the major hurricane is most important or one just hitting the region, or whether losing one decision maker is just as impactful as losing a majority. The important thing is to formally incorporate rare events into your project planning because we handle the normal stuff well. Rare events make or break major projects.